schedule of works
may, 2010
sat. 20: schedule setup + materials research + prototype “moment-piece” brainstorm
wed. 24: indivivudal economic, political and social pieces are to be fully modeled and printed using the 3d printer. process animation storyboard due
sat. 27: printed individual pieces and prototype assembly. prototype animation work day
wed. 31: exhibit prototype and process animation due. figure out material quantities and place order before april 1
april, 2010
wed. 14 – wed. 21: working on final model assembly and sketching experiential diagrams. continuing work on process animation
wed. 28 – wed. 5: final model assembly and production of final experiential diagrams. finishing touches on process animation
wed. 5: final model + experiential diagrams + process animation due